Can you envision something that is 12 million square feet?

That’s how large a proposed data center campus would be in Georgia, ranking the plan among the most expansive pitched across the state.

Developer Trammell Crow Co. is planning a $21 billion technology campus for a 1,632-acre site along I-75 in the city of Forsyth, roughly 60 miles southeast of downtown Atlanta. A state infrastructure filing unveiled the early-stage project Wednesday, but details are scant.

The project called the Forsyth Technology Campus could include up to 12 million square feet of buildings spread across 21 data center warehouses that store computer servers, according to a rezoning application obtained by The Atlanta Journal-Constitution.

At that scale, it’s hard to make comparisons.

The average Atlanta home is about 2,200 square feet, so it would take more than 5,400 homes to match 12 million square feet. Atlanta’s tallest building, Bank of America Plaza, has about one-ninth of the floor space at 1.3 million square feet. More than seven Lenox Square malls could fit within the proposed Forsyth project.

An aerial view captures a large area under construction for a new data center campus on Thursday, May 29, 2025. Developed by QTS, the data center campus near Fayetteville is one of the largest under construction in Georgia. (Miguel Martinez/AJC)

Credit: Miguel Martinez-Jimenez

icon to expand image

Credit: Miguel Martinez-Jimenez

Trammell Crow, which is pursuing a similarly massive data center campus near Augusta, declined to comment about the Forsyth Technology Campus. The Texas-based developer is also pursuing a 2.3 million-square-foot data center project in Douglas County.

Forsyth, a small town with about 4,600 residents, is along a stretch of I-75 between Atlanta and Macon that has become a hot spot for sprawling data centers. Multibillion dollar industrial projects are in various stages of development in neighboring Butts and Lamar counties.

The Atlanta area has emerged in recent years as one of the fastest-growing data center markets in the world. It ended June as the second-largest in the world behind only Northern Virginia, according to data from real estate services firm CBRE.

The industry’s rush into Georgia has sparked controversy, both statewide and locally. State lawmakers have considered revamping incentives designed to recruit data centers, while utility regulators and environmental watchdogs have scrutinized their power needs. Several communities have issued moratoriums to pause new data centers amid local opposition from concerned neighbors.

Trammell Crow seeks to rezone the Forsyth project site along Johnsonville Road, Smith Road and Collier Road west of I-75. The request triggered a Development of Regional Impact review, an infrastructure study required for most large projects.

This is a site map of the proposed Forsyth Technology Campus in Monroe County along I-75. (Courtesy Trammell Crow Co.)

Credit: Courtesy of Trammell Crow Co.

icon to expand image

Credit: Courtesy of Trammell Crow Co.

Regional commissions, which conduct the review, received new guidance last week on how to evaluate data centers following a monthslong pause on accepting new projects into the DRI process.

The Forsyth project is estimated to generate $1.4 million in annual local tax revenues during the first years of development, the rezoning application said. When fully built out, it is projected to generate $222 million in annual taxes, including $21 million for Forsyth.

It’s unclear whether Trammell Crow is pursuing any tax breaks or other incentives.

Forsyth’s 2025 budget shows it anticipated total revenues of $12 million for the year, meaning the project could nearly triple the city’s tax collections when finished.

“Based on current tax estimates, Forsyth Technology Campus is expected to become the single largest taxpayer in Monroe County while producing one of the lowest impacts to public services of any major development in the county,” the rezoning application said.

The project is expected to employ 500 to 700 employees, according to the application. The technology park is also projected to use up to 1.5 million gallons of water per day, according to the DRI.

“Water demand for technology facilities vary greatly based on the need for cooling and cooling approach,” a city employee wrote in the DRI. “The design team will work with watershed management and their modeling to establish an achievable demand and adjust the cooling approach as necessary.”

The project’s completion timeline is listed in the DRI as 2037, indicating a multiyear phased approach.

About the Author

Keep Reading

Cooling towers for Units 4 and 3 are seen at Plant Vogtle, operated by Georgia Power Co., in east Georgia's Burke County near Waynesboro, on Wednesday, May 29, 2024. (Arvin Temkar/AJC)